Typical Manufacturing Project Life Cycle

STEP DESCRIPTION CUSTOMER ACTION OUR ACTION TURNAROUND
1 Quoting Fills in RFQ form and provide product design (2D/3D) for us to provide a quote. Engineering studies RFQ and provides quotes based on volume. 1-2 weeks.
2 Project go-ahead Approves our quote. Project kick-off.
3 Design & specs update Sends latest CAD drawings, design notes, and specifications.   3D (igs/stp)/ 2D (dxf/dwg) drawings for casting, machining and finishing are preferred.
4 Tooling design Provides tooling design guidance or transfers existing tooling. Designs new tooling or modifies existing tooling. Provides new tool design drawings for approval. 1 week.
5 Build/modify tooling Reviews and approves tooling design. Builds or modifies tooling.

- New tooling: 30-60 days.

- Modification of existing tooling: 3-15 days.

6 First sample production Examines first production sample from us to determine if any modifications are needed (e.g., minor sizing adjustments). Changes tooling based on customer feedback. 3-15 days.
7 First batch production Examines first production batch and approves production readiness. 2-3 weeks.
8 Production Places order and schedules production.